  • After upgrading to SCDPM 2012 sp1 from 2012 scheduled Exchange 2010 databases recovery points don't run or fail they are just skipped.  I've deleted and recreated a new protection plan with different setting and no recovery points are created. 
    Thursday, August 1, 2013 9:46 PM

Answers

  • Turns out after looking at the log files that someone changed the service account so the DPM sql database didn't have the correct permission for the DPM service account.
    • Marked as answer by w Worsley Thursday, August 15, 2013 5:49 PM
    Thursday, August 15, 2013 5:49 PM

All replies

  • Hi

    Have you updated your agents?

    Are any errors logged when you try run a manual backup?

    Thursday, August 15, 2013 5:08 PM
  • Turns out after looking at the log files that someone changed the service account so the DPM sql database didn't have the correct permission for the DPM service account.