Hi,
I found a strange behavior in Project Center. We have a formula for Finish based on Baseline and Actual Finish. If the schedule is on track then the indicator is Green and its working properly.
1. But in Some projects it is coming as Dark Green Indicator even i didn't used it any of my indicators at all.
2. When the projects move from one stage to another through Workflow, in some cases the indicators are disappearing. Even though there is no changes in dates.
3. While Base-lining in certain projects the Project summary is not getting base-lined. I did it through the baseline command only and selected whole project.
Any ideas?? Or is this a common issue :(
Thanks & Regards, Benno