    I don't know why monthly cost distribution starts 1 month before the schedule.

    Start time is January but in task usage, cost are distributed 1 month before as shown in the capture.

    Thanks.


    • Edited by selcukz Tuesday, December 17, 2013 1:20 PM
    Tuesday, December 17, 2013 1:19 PM

All replies

  • selcukz --

    Though you did not say explicitly, it appears from your screenshot that you are using Microsoft Project 2013.  Assuming that is the case, what you are seeing is a bug that has been fixed in one of the Cumulative Updates.  Therefore, I would recommend that you apply the latest Cumulative Update to your copy of Microsoft Project 2013 and this should fix the problem.  Hope this helps.


    Dale A. Howard [MVP]

    Tuesday, December 17, 2013 1:56 PM
    Moderator
  • Thanks Dale,

    It the updates fixed the problem,but there is a new problem now.It's very important. When i try to write the monthly costs manually to the task usage table's "cost" cells, project is stopped the working and a box appears and says ; "restart working" 

    This is terrible and i cannot work now.Everything stopped. :(

    I wish you help me. THANKS

    the box is like that. 

    Wednesday, December 18, 2013 9:28 AM
  • Please update Project professional 2013 with latest Oct CU .

    kirtesh