Microsoft Project Standard 2013 Calendar Options RRS feed

  • Question

  • Is there a way to print the Calendar and include the Sales Manager's name that has been assigned the task? I have the name entered in the program but my boss wants to see who is assigned what task on which days.

     
    Tuesday, January 5, 2016 11:04 PM

All replies

  • Task usage view?

    Resource usage view?

    Tuesday, January 5, 2016 11:21 PM
  • dmedlin,

    If you are referring to the Calendar view, then yes, go to Format/Format group/Bar Styles and enter the fields that you want to show in the text section.

    Hope this helps.

    John