none
PWA - TIMESHEET ISSUE - INSERT TASK - TASK SELECTED BUT DOES NOT GET ADDED TO TIMESHEET RRS feed

  • Question

  • A resource is assigned to a task that appears on his future timesheets.  We are trying to insert it onto a prior timesheet.  When we select Insert Row->Insert Task->Add an Existing Task the project and the task show.  We select the task and click OK.  Nothing happens, the task is not added to the timesheet.

    The timesheet was recalled.The start date of the task is prior to the time period we are trying to add it to.  The resource has remaining hours on the task.  The resource is the Assignment Owner on the task. 

    Not sure what else to check.  Any assistance/suggestions would be appreciated.  Thank you 

    We are on 2010

     
    Wednesday, April 9, 2014 9:13 PM

Answers

  • Hello,

    If the timesheet does not have any admin time (Holiday, sickness... ect... ) then please try delete the timesheet period and re-create the timesheet. Any time added to tasks will remain stored and will appear when created again.

    You will need to recall the timesheet to be able to delete it.

    • Marked as answer by dennykat Tuesday, September 9, 2014 1:46 PM
    Monday, September 8, 2014 9:06 AM