Deliverables and Dependencies in Project Server 2013 RRS feed

  • Question

  • Hi,

    In a project connected to Project Server 2013 (On Premises) I created a Deliverable and after 5 minutes (a little bit slow) I saw the typical icon of Deliverables in the Indicators column of Project Pro, as well the bar symbol in the Gantt chart.

    In another project I created a Dependency on this first deliverable. The system tells me the dependency has been created but there is no icon in the Indicators column and there is no symbol bar in the Gantt Chart. The Deliverable Excel report displays the (blank) value for Consumer Task Name and for Consumer Start Date.

    Is this a bug or am I missing something?

    Thanks

    Sunday, October 20, 2013 10:49 AM