Project 2010 - Timesheet Actual Hours does not equal Actual Work. RRS feed

  • Question

  • We have noticed descrepancies between the actual hours booked in our timesheets and the
    actual hours showing in our project plans.

    Example:
    • A employee booked 9 hours against task 'Backup Database' in a Project called 'Maintenance'
    • The timesheetline and timesheet is approved by the Timesheet manager.
    • The project plan is reviewed and the plan published.

    When I investigate the values in the reporting database, I notice the following;
    • The 'Actual Billable Work' in  [MSP_Project_Timesheet] cube is 9
    • The 'Actual Work' in  [MSP_Project_Timesheet] is 8.862223

    Our working days are Mon - Friday, 7.5 hours per day.  

    Can anybody tell me why this is happening?

     

    Wednesday, November 10, 2010 7:45 AM

Answers

  • Hi,

    Can you please check in the project plan what the value for Actual Work is for this task?
    Have the hours been entered as hours, or did you enter them as a 'days' value?

    Make sure to check all calendar related settings:

    • Calendar Definition
    • Schedule settings in Project Pro for this project (Tools -> Options -> Schedule)
    • The Default Reporting Units (number of hours per day) in 'Timesheet Settings and Default' (PWA -> Server Settings)

    Make sure all these settings match your 7.5 hours per day calendar.

    What version of Project Server are you using?

    I hope this helps,
    Hans


    My EPM blog: Projectopolis
    • Marked as answer by Mike Glen Wednesday, November 9, 2011 10:26 PM
    Wednesday, November 10, 2010 8:06 AM

All replies

  • Hi,

    Can you please check in the project plan what the value for Actual Work is for this task?
    Have the hours been entered as hours, or did you enter them as a 'days' value?

    Make sure to check all calendar related settings:

    • Calendar Definition
    • Schedule settings in Project Pro for this project (Tools -> Options -> Schedule)
    • The Default Reporting Units (number of hours per day) in 'Timesheet Settings and Default' (PWA -> Server Settings)

    Make sure all these settings match your 7.5 hours per day calendar.

    What version of Project Server are you using?

    I hope this helps,
    Hans


    My EPM blog: Projectopolis
    • Marked as answer by Mike Glen Wednesday, November 9, 2011 10:26 PM
    Wednesday, November 10, 2010 8:06 AM
  • Hi Lulu,
     
    Next time, try posting on the Project Server General Questions and Answers forum:
    http://social.technet.microsoft.com/Forums/en-US/projectserver2010general.  Please see FAQ Item: 52 Find a Forum.   FAQs, companion products and other useful Project information can be seen at this web address:  http://project.mvps.org/faqs.htm
     
    Mike Glen
    Project MVP
     
     
    "Stunned Lulu" wrote in message news:1f8f2f44-be0a-4e95-abb2-29e2b3d10875@communitybridge.codeplex.com...
    We have noticed descrepancies between the actual hours booked in our timesheets and the
    actual hours showing in our project plans.

    Example:


    * A employee booked 9 hours against task 'Backup Database' in a Project called 'Maintenance'
    * The timesheetline and timesheet is approved by the Timesheet manager.
    * The project plan is reviewed and the plan published.
    When I investigate the values in the reporting database, I notice the following;


    * The 'Actual Billable Work' in  [MSP_Project_Timesheet] cube is 9

    * The 'Actual Work' in  [MSP_Project_Timesheet] is 8.862223
     

    Our working days are Mon - Friday, 7.5 hours per day. 

    Can anybody tell me why this is happening?

     
    Wednesday, November 10, 2010 4:08 PM
  • Thanks Hans

    The value of the Actual Work in the plan is 8.87

    Checked everything else related to the calendar, all is set to 7.5 hours

    Version: MSO 14.0.4751.1000

    Regards

    Lulu

     

    Thursday, November 11, 2010 2:59 AM