Error in adding holidays to Project Calendar RRS feed

  • Question

  • When I add a 2 week xmas holiday to the calendar in Project, it shifts my project out 15 years. I did individual days once a year. Here are the lines that seem to make the jump.

    Task Name Duration Start Finish Predecessors
    49 Generate & Review Documentation 3 wks Wed 8/6/14 Tue 8/26/14 46
    50 Approve Documentation 0 days Thu 4/12/29 Thu 4/12/29 49FS+1 wk

    Any suggestions on what I'm doing wrong?

    Wednesday, September 24, 2014 7:25 PM

All replies

  • Hi,

    Which version and Service Pack do you use?

    Is the calendar applied to a task, a resource or the project?

    Have you checked that the calendar is correctly configured?

    Can you reproduce the issue ony any task? Any project?

    Would it be possible that by error you splitted the task with your mouse and that the cursor went away to the far right of the Gantt chart so the task was extended to 2029?


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Thursday, September 25, 2014 2:49 AM
    Moderator