  • hello

    i sai, i has problem for duration that to setting with 4 days but the date show only 2 days. this in the project information at the calendar setting 24 hours. how i need to to setting back to normal. or can i setting back the project like to new i has installed?

    

    https://social.technet.microsoft.com/Forums/getfile/1059844

    Monday, May 8, 2017 5:11 PM

All replies

  • sailangsi --

    The software is working as expected.  To make the Duration value match the time span from the current Start date to the current Finish date, you would need to do the following:

    1. Click File > Options.
    2. Click the Schedule tab.
    3. Set the Hours Per Day value to 24 and then click the OK button.

    Hope this helps.


    Dale A. Howard [MVP]

    Monday, May 8, 2017 10:14 PM