Inconsistent oData coming from Task and Assignment Timephased RRS feed

  • Question

  • Hi Guys, 

    I'm having a problem on why my TaskTimephased and AssignmentTimephased are getting different data. My hypothesis is that the TaskTimephased doesn't refresh properly because upon checking the values side by side with Project Professional the data in AssignmentTimephased is correct and TaskTimephased is not. 

    Also a work around I notice is to put the % Work Complete of a task to 0 then publish then put it back to the original then publish would fix for that task. 

    Any other easier way to solve this problem? 

    Edit: The Tasks oData is retrieving the correct data so only the TaskTimephasedDataSet is showing the wrong values
    • Edited by FranzJustin Tuesday, June 11, 2019 4:51 PM Added information