Want to Change a Working Day to Non-Working Day -- But it is Grayed Out RRS feed

  • Question

  • I want to change a working day to non-working day, but the area in the "Exception" section will not let me click inside the box to make an exception. 

    How do I get this to allow me to type? I am using MS Project 2010. Thanks!

    Wednesday, January 15, 2014 8:26 PM

All replies

  • If you are using Project Server, only administrators can manage enterprise or resources calendars.

    If it is the case, please update the enterprise calendar (or resource calendars) from PWA or ask your administrator to do so.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Wednesday, January 15, 2014 8:37 PM