Project 2010 - Linking tasks from one project to a task on another project RRS feed

  • Question

  • Hello,

    I have set up a master project that I have set out a number of tasks.  I would like to link a number of tasks from two other projects as predecessors for the task in my master project.   

    For instance, Master Project has tasks A, B, C, D, E.  Sub Project #1 has tasks a,b,c,d,e and Sub Project #2 has tasks i, ii, iii, iv, v. I would like to reflect Master Project A is dependent upon tasks Sub Project #1 a & c and Sub Project #2 ii & v.  And I would prefer not to show the long list of tasks from the Sub Projects in my Master Project.   

    Is there a way to do this? 

    Thank you in advance.

    Thursday, May 4, 2017 6:45 AM

Answers

All replies