Connect Project Server 2010 to an external system for Holiday Information RRS feed

  • Question

  • Hi All

    I would like to connect our Project Server Environment to an external business system that employees use to request holidays.

    How would I go about this?

    It would basically sync to the enterprise calendar showing all resource holidays.

    Is this even possible? Or am I thinking the wrong way about it?

    Thanks for any help offered

    Thursday, June 27, 2013 1:59 PM

All replies

  • Hi,

    sure that's possible. You can use PSI to add admin time as calendar exceptions.

    Best,

    Renke


    http://www.holert.com Project Management with MS Project - Oldenburg, Berlin, Munich/Germany

    Thursday, June 27, 2013 8:20 PM
  • HI Renke

    Thank you for your reply

    So I would create a PSI extension to the external business system to bring in employee holiday data to match it to resource holidays?

    Is that correct?

    Friday, June 28, 2013 8:24 AM