  • Hi,

     

    I have a resource who is now 200% (2 people) - for the next 2 month - it will be 100% and then back to 200%.

    how can I change it in?

     

    Thanks,

    Hanni


    Hanni, PMO
    Thursday, March 3, 2011 3:49 PM

Answers

  • Hanni --

    Navigate to the Resource Center page in PWA, select this resource, and then click the Open button to open the resource for editing in Microsoft Project 2010.  Double-click the name of the resource in the Resource Sheet view.  In the Resource Availability section of the Resource Information dialog, specify the resource availability changes over time.  Click the OK button, then save and close the Enterprise Resource Pool.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, March 3, 2011 4:32 PM