Reported Items on Task with Percent work (and percent complete) are both zero RRS feed

  • Question

  • My schedule (incorrectly?) notifies me I have reported progress on a task when I try to delete a resource.  Though Percent complete and Percent Work complete columns are zero.  This prevents my schedule form autocacualting.  When I delete and reassign a resource the schedule autocalculate.


    Wednesday, August 7, 2013 4:34 PM

All replies

  • Brian --

    If the task has an Actual Start date but no Actual Work applied, that would cause the warning message you see.  Hope this helps.


    Dale A. Howard [MVP]

    Thursday, August 8, 2013 11:28 PM