What is the Fastest way to rebuild a corrupt project schedule? (2007) RRS feed

  • Question

  • Hi

    A client has built a large project plan that is corrupt.  What is the fastest way to take all the data and import it into a new MPP file?

    need the following:

    -resources

    - resoruce calendars

    - filters

    - text styles

    - custom fields

     

    Thank you!

    ~Dora

     

    Thursday, July 14, 2011 8:46 PM

Answers

  • Nevermind!  I did the following and it fixed my issues:

    1) Copied my Entry table to 'Entry2'

    2) Switched to a different view other then Gantt

    3) Copied both the 'Entry' table and "Gantt' view from the gloabl MPT into my current file via Organizer

    4) Changed my view back to Gantt and appied my "Entry2" table.

    5) Added my text styles back. (Blue for milestones, Red for Critical Tasks)



    Thursday, July 14, 2011 9:01 PM