MS Project Professional and Project Server RRS feed

  • Question

  • I try to connect MS Project Professional 2013 with MS Project Server 2010 and I cannot do this. I want to use 2010 Server option, because I heard 2013 Server need many hardware resources.
    Monday, September 2, 2013 6:35 PM

Answers

  • Elena --

    You cannot connect Microsoft Project 2013 to Project Server 2010.  You must connect using Microsoft Project 2010 only.  Hope this helps.


    Dale A. Howard [MVP]

    • Marked as answer by Elena Belen Monday, September 2, 2013 6:38 PM
    Monday, September 2, 2013 6:37 PM
    Moderator
  • MS Project Professional 2013 does not connect to MS Project Server 2010.

    You can connect next software versions:

    • MS Project Professional 2013 with MS Project Server 2013 or
    • MS Project Professional 2010 with MS Project Server 2010
    • Marked as answer by Elena Belen Monday, September 2, 2013 6:37 PM
    Monday, September 2, 2013 6:37 PM

All replies

  • MS Project Professional 2013 does not connect to MS Project Server 2010.

    You can connect next software versions:

    • MS Project Professional 2013 with MS Project Server 2013 or
    • MS Project Professional 2010 with MS Project Server 2010
    • Marked as answer by Elena Belen Monday, September 2, 2013 6:37 PM
    Monday, September 2, 2013 6:37 PM
  • Elena --

    You cannot connect Microsoft Project 2013 to Project Server 2010.  You must connect using Microsoft Project 2010 only.  Hope this helps.


    Dale A. Howard [MVP]

    • Marked as answer by Elena Belen Monday, September 2, 2013 6:38 PM
    Monday, September 2, 2013 6:37 PM