Deleted "Usage" table in Project 2010 Organizer; how do I get it back? RRS feed

  • Question

  • I have deleted the "Usage" table from Project 2010 Organizer by accident.  I now am unable to view "Task Usage" and "Resource Usage."  How do I get the table back?  I have uninstalled and reinstalled with no success on retrieving the table.
    Saturday, December 3, 2011 2:08 PM

Answers

  • Pls follow the procedure described in the thread below to delete Global.mpt:

    http://social.microsoft.com/Forums/en-US/projectprofessional2010general/thread/aa80a103-90da-47f6-8179-730cfd2b75e1


    Saturday, December 3, 2011 3:12 PM

All replies

  • Pls follow the procedure described in the thread below to delete Global.mpt:

    http://social.microsoft.com/Forums/en-US/projectprofessional2010general/thread/aa80a103-90da-47f6-8179-730cfd2b75e1


    Saturday, December 3, 2011 3:12 PM
  • Just a quick comment -- be aware that deleting the local copy of the Global.mpt file means all other customizations will be lost.  You may wish to do as John suggests, rename the file and store somewhere else to restore any other customizations after deleting and re-creating the Global.mpt file.

    Julie

    Sunday, December 4, 2011 5:05 PM