Can Assignment fields be Synchronizing with a Sharepoint Task List RRS feed

  • Question

  • Hi

    I understand that only the fields that are mapped between the MS Project and Sharepoint task list will synchronize and that following fields will sync by default:

    • Task Name
      Start date
      Finish (due) date
      % Complete
      Resource Name
      Predecessor

    However, can other Task List fields be set up to "synchronize" at the assignment level in MS Project?  i.e., an assignments Default Start, Actual and Remaining Work or Duration?  I am wondering if assigned resources can update their status using "Actual Work" and "Remaining Work" in a SharePoint Task List as they would in the My Task PWA page versus using the "% complete" in Task List.  Any thoughts/ comments are welcomed.


    \Spiro Theopoulos, Montreal, QC (Canada)

    Saturday, August 6, 2016 2:51 PM