2010 automatically expands all my subtasks in a 2003 project plan RRS feed

  • Question

  • Guys,

    When I open or edit the indent levels of a task in my 2003 Project file in MS Project 2010, 2010 expands all my subtasks and doesn't save the way I've kept my expansions/contractions.

    Is there a way to resolve this?

    scott



    • Edited by Scott Frase Thursday, January 3, 2013 8:36 PM
    Thursday, January 3, 2013 2:35 PM

Answers

All replies

  • Please install June 2011 hot-fix for 2010, it has resolved this issue. http://support.microsoft.com/kb/2536590

    Sapna Shukla

    Thursday, January 3, 2013 2:43 PM
    Moderator
  • Sapna,

    Will do.  Let u know how it goes.

    thanks,

    scott


    Scott Frase

    Thursday, January 3, 2013 8:04 PM
  • Sapna, The patch works in my first QA of the software. thanks much, scott

    Scott Frase


    • Edited by Scott Frase Thursday, January 3, 2013 8:49 PM
    Thursday, January 3, 2013 8:35 PM
  • Sapna,

    I was editing my project plan all day and it seems to now be corrupted somehow.  The error states "No calculations can be performed now.  There is a circular relationshipo in task 852.  The successors of this task refer back to this task or its predecessors, causing a circular reference."

    When I open the file, it has only ~260 tasks.  This project plan used to have 1500+ records.  I made a backup of the file a month ago, but have invested many hours into the file.

    can you take a look at it and see if it is salvageable?  how can I upload it to you?

    scott


    Scott Frase

    Friday, January 4, 2013 6:52 PM
  • doing now..

    Scott Frase

    Friday, January 4, 2013 7:22 PM
  • OK..sent, along with an export to an XLSX file, just to show you that there are about 1700 tasks in the pp.

    Scott Frase

    Friday, January 4, 2013 7:41 PM