Project Finish Date in Project Information window and Project Summary Task are different RRS feed

  • Question

  • Hi,

    I have seen a strange issue in MS Project 2010 Pro today. Its about Project Finish date behaviour in Project summary task and in project information window. I could see different dates at both the places.

    What could be the reason? MS Project 2010 Pro & Project Server 2010 are updated with June 2012 CU and Plan opend from Project Server 2010.

    Any help will be appreciated.


    Thanks, Ram

    Sunday, May 12, 2013 6:37 AM

All replies

  • Hi Ram,

    Is this a Master Plan or linked to some other plans?


    Sapna Shukla

    Sunday, May 12, 2013 9:02 AM
    Moderator
  • Hi Sapna,

    No. It is an individual project and it has not been linked to any other projects.

    Do we see similar issue with Master & Sub Project plans?


    Thanks, Ram


    Sunday, May 12, 2013 10:40 AM
  • What is mode of updates to actuals - through plan, timesheet or PWA?

    Sapna Shukla

    Sunday, May 12, 2013 11:27 AM
    Moderator
  • Thanks for you reply, Sapna.

    We have been updating the plan through PWA and MS Project. 


    Thanks, Ram

    Sunday, May 12, 2013 1:04 PM
  • This can easily happen to have the finish date different on the plans.  If you publish your project, the finish date will seen as suggested.  However, if when working in project professional you make adjustment to the schedule, he finish date can change.

    Publish you project again and see if they match up.

    Cheers!


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Sunday, May 12, 2013 7:19 PM
    Moderator