Project Server: Synchronization of AD with security groups timer job is missing RRS feed

  • Question

  • Environment: Project Server 2013

    Issue: Project Server- Synchronization of AD with security groups timer job is missing in Central Admin

    Do you guys know how can i fix it and why it is not showing up?I used powershell scrip by using"Invoke-SPProjectActiveDirectoryGroupSync" command but how can we fix through UI.

    Thanks!


    Thursday, July 10, 2014 5:24 PM

All replies

  • Can you try disabling the group Sync for the PWA group, save the changes and then try enabling it by adding the group again.


    Cheers! Happy troubleshooting !!! Dinesh S. Rai - MSFT Enterprise Project Management Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you. This can be beneficial to other community members reading the thread.

    Thursday, July 10, 2014 6:02 PM
  • In addition to Dinesh's suggestion, Also make sure that "Enable Schedule Synchronization" option is selected please let us know what is the current CU level of your Project Server, since this issue was fixed OCT 2013 CU

    http://support.microsoft.com/kb/2825659

    Although you can set up Active Directory group synchronization in Project Server 2013, the timer process never starts, and the security groups are never synchronized."


    Hrishi Deshpande Senior Consultant

    Friday, July 11, 2014 1:59 PM