On Time Delivery OTD (Project and Tasks) RRS feed

  • Question

  • Hi,

    Does project timestamp changes of statuses if a project status is changed from active to complete? I have the same question about tasks. If you change the status to 100% complete on a task, press check-in & publish. Is that completion date reflected in the data, or would I have to add a field called "actual date" to be manually entered upon completion?

    What are my options?

    /Henrik

    Thursday, April 5, 2018 12:59 PM

All replies

  • Hi Henrik

    Yes, this is known. 

    If you add a date type custom field with the calculation of =Now(), then that field will always update on Save or Publish.  Does not fix the broken code from MS for not marking the Project Last Modified date field, but does give you a value to look at in reporting or on a Project Center view.

    Hope this helps,


    Thanks, Eric S. Pcubed

    Friday, April 6, 2018 3:50 PM