none
Resource Cost update RRS feed

  • Question

  • We are just in the process of setting up MS Project Server 2010. I discovered several of my resources did not have a standard or overtime cost set up - but I did not make the discovery until after they had timesheets entered and approved. Now I have a number of tasks that have hours applied, but show $0 cost. I have gone back and updated the resource costs. How do I get the task costs to update?

    Thanks for the help,

    Mike Ernst

    Friday, April 13, 2012 9:13 PM

All replies

  • All the applicable project plans need to be re-published to be able to view the costs in PWA.

    In project professional, these should be calculated automatically when you open the plan.


    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    Friday, April 13, 2012 9:16 PM
    Moderator
  • I don't believe existing timesheets will be updated - you'll need to manually calculate these values.

    Ben Howard [MVP] blog | web

    Monday, April 16, 2012 9:18 PM
    Moderator