  • Question

  • In my project my resource is worker.

    I would like to level automatic my project with the constraint of 900% of worker unit for each week of the project.

    How I do this?


    • Edited by GioG Sunday, March 25, 2018 10:14 AM
    Sunday, March 25, 2018 10:13 AM

All replies

  • Hi,

    You would set the worker max unit to 900% in the resource sheet. Then do your schedule setting the tasks to fixed unit.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Sunday, March 25, 2018 10:56 AM
    Moderator
  • GioG,

    I notice you use the term "worker" which implies you mean one person. There is no way to have a single resource at more than 100%. However if you really mean workers (more than one person, such as a team), then the Max Units on the Resource Sheet can be greater than 100%.

    Just wanted to clarify.

    John

    Sunday, March 25, 2018 3:52 PM