Summary Task shows 99% RRS feed

  • Question

  • I have all tasks scheduled for 1 day but marked as milestone. All tasks are 100% completed but summary task shows 99%. What can I do to change it to 100% complete?
    Tuesday, December 20, 2011 9:17 PM

Answers

  • Hi Mimi,

    I have seen this occur occasionally in Project 2010.  A couple of things to check.

    Display the Tracking table and make sure that all tasks have zero remaining duration and zero remaining work.  If you have any milestones (true 0 day duration tasks) make sure they are all 100% complete as well.

    If all tasks show zero remaining work and zero remaining duration, if you change the duration of one of the tasks from 100% to some other value and then change back -- does it update correctly?

    Julie

    Tuesday, December 20, 2011 10:12 PM
    Moderator