Custom WBS codes missing in projects RRS feed

  • Question

  • Hi!

    I have Project Server 2010 instance with couple of projects published on it and a group of planners working with projects in Project Proffessional 2010 connected to MSPS. A custom WBS code structure like Proj.Stage1.Task1.*.* is set in every project.  Trouble is that in some project stages WBS is missing completely, the field is clear and I can`t reproduce the situation to troubleshoot it. Planners are working, approving task updates, updating and publishing projects as usual.

    WBS is used in SSRS to buld reports. If WBS is off, the reports are down..

    What is it might be?


    Tuesday, July 8, 2014 4:54 AM