Is "Baseline Date" stored anywhere in the 2010 Draft/Published/Reporting Databases? RRS feed

  • Question

  •     I have a need to display Baseline Date in views and reports, but can't find anything in Reporting DB, or available fields in PC views that has it. This is a pretty important piece of information IMHO, and as of now, we have to open each Project individually (PWA or MSP) to see if baseline "0" has been set.

        Is a macro in MSP 2010 that populates an Enterprise Custom Project field the ONLY way to get this date visible to the Enterprise?  With all the other stuff in Reporting, I can't fathom why that was left out!!!!!

       Thanks!

    Jackson T. Cole


    JAckson T. Cole, PMP, MCITP

    Thursday, March 19, 2015 1:56 PM