Can a person that owns the plan give access to someone else to update the plan as well in project server 2010?? RRS feed

  • Question

  • Hi,

    Can a person that owns the plan give access to someone else to update the plan as well in project server 2010?

    Is there any possible way to do it .

    Thanks in advance.


    Regards, Anurag

    Wednesday, January 9, 2013 12:41 PM

All replies

  • Hi Anurag,

    the project owner can use "Project Permissions", located in the ribbon in Project Center to grant permissions to other user.

    What you cannot do by this is to define someone else, who approves an update for an assignment sent by the resource. For this either the status manager has to be changed on task level when needed, or you have to use the delegate functions.

    Hope that helps

    Regards

    Christoph