  • Hi,

    I need a field in MS Project 2013 which shows the (Planned work-Baseline Work) in percentage.

    May I know how to do that?


    K.Gokulraj

    Tuesday, September 8, 2015 10:40 AM

All replies

  • Is this article helpful or you need something else?
    Tuesday, September 8, 2015 10:55 AM
  • Hi,

    Thanks for you reply.

    In the above picture you can see a column called (% Actual)which is actually (% work complete field in MS Project) and "% Expected" column is "baseline work" field in MS Project.

    So my requirement is, an Enterprise custom field needs to be created which represents the Baseline work but the value in that field should be in "%" not in hours


    K.Gokulraj

    Tuesday, September 8, 2015 12:00 PM
  • So the problem is which is the mathematical expression, not how to create a custom filed. Correct?
    Could you please some test data about what you have available and what you must show? for example the baseline work in the MS Project what represents?