Adding time worked on projects for all team members RRS feed

  • Question

  • Is there a way in Project Online to allow Project Manager's to add time to the timesheet's of each person on their team?  If not, can it be done in Project Professional and populated into Project Online?


    SharepointJP

    Thursday, February 25, 2016 6:49 PM

Answers

  • Hi,

    if a PM enters Actual work for resources in client using Task Usage view, this Actual Work will be transferred to /tasks.aspx, as long as administrator has not enabled "Only allow task updates via Tasks and Timesheets" in Server Settings - Task Settings and Display.

    If timesheet is created afterwards, this Actual Work will be included in Timesheet, if administrator has not changed default setting for timesheet creation "Current task assignments" in Server Settings - Timesheet Settings and Defaults.

    Not sure if that helps?

    Maybe we need more information about the background of your question.

    Regards
    Barbara


    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find an appropriate solution faster. Thanks for your support!