SPI and CPI indicators not working for some tasks in MSProject 2007 Enterprise RRS feed

  • Question

  • I have inherited a project. UAT had to be repeated. I inserted a task, which I have baselined. The CPI and SPI indicators for the task or any of the tasks following that task are calculating. When I check the Custom Fields for the task, it reads that the CPI and SPI Ind Task as #ERROR.

    Any ideas as to what that means and how to correct it?

    Thank you.

    Friday, June 20, 2014 3:11 PM

All replies

  • Hi,

    I'm afraid your explanation is not clear to me...

    When you say "custom fields", are you talking about the out-of-the-box CPI and SPI fields? Or custom fields created by you with a formula?

    When you mention the task, it is a newly created task?

    Does it have any specificities? 

    Can you reproduce this issue on a brand new project?


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    Friday, June 20, 2014 3:21 PM