Project 2016 - Cash Flow Report customization RRS feed

  • Question

  • Hi, In this out of the box Project client report I want to add a custom enterprise field from the task list. Is there a way to include fields available from both tasks and Resources field list? It seems I can only display values from the Resources List OR Tasks List.
    Monday, July 10, 2017 5:59 PM

All replies

  • smlopes --

    The default Cash Flow report is a Task Usage report, which means that only task fields are available for use in this report.  However, the good news is that if you want to include BOTH task and resource data in the report, you can create a new extended Cash Flow report by creating a new template using Assignment Usage data.  Hope this helps.


    Dale A. Howard [MVP]

    Monday, July 10, 2017 9:04 PM