Sharing schedule WITHOUT sharing resource allocation information RRS feed

  • Question

  • Good day All,

    Can anyone tell me if it is possible to share my project schedule data with a customer WITHOUT sharing the allocation information that has been assigned to the project?

    TIA,

    James


    Monday, January 6, 2020 6:29 PM

Answers

All replies

  • JD --

    Why don't you save a second copy of the project and then delete all of the resources in the Resource Sheet view of the project?  And then send that to the customer.  Just a thought.  Hope this helps.


    Dale A. Howard [MVP]

    Monday, January 6, 2020 7:32 PM
    Moderator
  • Thank you Dale. Yes, that was my first thought but that would mean maintaining 2 separate schedules as things change. I am hoping that there is someway to "hide" the resource allocation tables. 
    Monday, January 6, 2020 7:45 PM
  • JD --

    It's not possible to hide the resource allocation information in Microsoft Project.  Sorry.  Hope this helps.


    Dale A. Howard [MVP]

    Monday, January 6, 2020 8:35 PM
    Moderator
  • Thank you Dale. 
    Tuesday, January 7, 2020 3:25 PM
  • JD --

    If one of my replies answered your question, would you kindly mark my reply as the answer?  Thanks much, my friend!


    Dale A. Howard [MVP]

    Tuesday, January 7, 2020 6:02 PM
    Moderator