    In a Project file, a task will be checked off as 100% complete.  I go Project > Reports > Assignments > Edit > Filter: Work Incomplete to run a report showing me the list of Incomplete tasks.  That 100% completed task appears in my Incomplete report.

    This happens for multiple tasks.

    Please help!

    LGHEALTH

    Friday, March 22, 2013 1:27 PM

Answers

  • That is because the Work Incomplete only filters out resources who have finished all their work, it doesn't filter out the completed assignments.

    The easiest way to get your data is to go to the Resource Usage view and insert the % Work Complete field. Click on the little down arrow next to the % Work Complete column and unselect 100%. You'll now only see resources with remaining work and what the remaining assignments are.

    Thanks,

    Heather

    Friday, March 22, 2013 10:21 PM