Interim baseline in gnatt chart RRS feed

  • Question

  • How i can view interim baseline bar  in gnatt chart using Msp 2010, kindly help me.......
    Monday, August 29, 2011 2:34 PM

Answers

All replies

  • g.gokuldoss --

    Display the Format ribbon, click the Baseline pick list in the Bar Styles section of the ribbon, and then select the Baseline whose Gantt bars you want to show.  Hope this helps


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Monday, August 29, 2011 3:05 PM
    Moderator
  • Dear Dale,

     

    Thanks for your reply, I tried your steps, its works only for normal baseline not for interim baseline.

    Kindly guide me..............

    Monday, September 5, 2011 11:39 AM
  • Hi,

    When you say Interim baseline are you talking about 11 default baselines or what?


    Sapna S
    Monday, September 5, 2011 12:22 PM
    Moderator
  • hi

    Ya its 11 baselines only, but i used it as interim baseline....

    but i could not see the interim baseline bars in gantt chat....

    Kindly suggest me......

    Tuesday, September 6, 2011 10:11 AM
  • If its 11 default baseline then as Dale suggested you can select it from the Bar Style, it shows all the 11 of them. But I guess you are talking about the Interim Plan that is saved using Tracking Option, in that case only the Start and Finish [Start 1-10/Finish 1-10] are saved and not all of the variables which are normally saved with the Baselines. In that case go to Bar Style and in Baseline Start select your desired Start i (1-10) and in Baseline Finish select Finish i (1-10). Hope this is what you were looking for and it helps.
    Sapna S
    Tuesday, September 6, 2011 10:29 AM
    Moderator