Some tasks allow users to be able to edit the %Work Complete in timesheet RRS feed

  • Question

  • I have a query. %Work Completed column in Project server Timesheet view is not read only. still some tasks allow users to edit %Work Complete in timesheet and some does not. Does this depends on the task types or the user permissions.


    • Edited by Nav Sahi Wednesday, June 17, 2015 5:40 PM
    Wednesday, June 17, 2015 5:34 PM

Answers

  • Got the reason If the task is manually scheduled, the % work complete column will be editable.