Project 2010 multiple task dependencies RRS feed

  • Question

    • Let's say I have 3 tasks, 1, 2 and 3.  I'm trying to make task 3 start when task 1 starts and end when task 2 ends.  Help?
    Sunday, August 18, 2013 6:20 PM

All replies

  • There's nothing really out of the box, other than manual intervention that would accomplish this.  Some folks have written macros to do the same.  For an example, check out the Project Widgets site - which has some sample macros.  The hammock task one sounds like it could help.

    http://www.projectwidgets.com/downloads/hammock.cfm


    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky

    Sunday, August 18, 2013 11:06 PM