Project Detail Dates showing as 41222.33333 in Project Server 2010 RRS feed

  • Question

  • The dates in Project server are showing up differently on different detail pages.  In some fields it shows correctly as

    1/26/2012 8:00 AM.  Then in the Dates Project Detail Page - the dates will show up as 40932.3333333333

    Any suggestions to fix this ??

    Thanks

    Friday, February 1, 2013 5:19 PM

All replies

  • Try deleting the values and re-entering date values.   Sometimes when pasting value into PDP fields there are many unprintable fields that effect displaying values.

    Cheers!


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Saturday, February 2, 2013 5:06 AM