Portfolio Analysis with Costs and Resources (2013) RRS feed

  • Question

  • Hi,

    Question about the two analysis: Costs and Resources. Are they independent or the Resource Analysis is working on projects previously selected by the Costs analysis?

    I have a lot of overallocated resources (red) but the Resource analysis doesn't suggest the hire any role. what did I miss?

    Thanks

    Saturday, September 26, 2015 10:08 AM

Answers

  • WLID1966,

    Resource Analysis works on the subset of projects selected in the Cost Analysis, and shows which of those projects could be taken up with the given resource constraints.

    As far as suggesting roles to hire, did you provide input as to how many resources you could hire first? The analysis module by itself does not provide this input.

    This presentation I made a Project Conference 2014 could be helpful: https://channel9.msdn.com/Events/Project/2014/PC252. Look at around 55:20 mark..


    Cheers,

    Prasanna Adavi, Project MVP

    Blog:   Podcast:    Twitter:    LinkedIn:   

    • Marked as answer by WLID1966 Saturday, September 26, 2015 2:39 PM
    Saturday, September 26, 2015 2:24 PM