Is it possible to produce a report in bespoke layout and output to Excel ? RRS feed

  • Question

  • Need to produce a Excel spreadsheet from Project 2010, which summarises by project how many days a resource has booked to it by month

    Is this possible ?

    Wednesday, March 13, 2013 8:55 AM

All replies

  • You could get this from the resource usage view in MS Project itself

    Right click on the grid on the right, select Actual Work, and zoom in/out until the columns show the values per month.

    Hope this helps,
    Andrew

    Wednesday, March 13, 2013 10:08 AM