Project Server 2010 - how to delete one timesheet? RRS feed

  • Question

  • User has entered timesheet, it and status have both been approved, and project has been published...

    how you you get back to the drawing board?

    I've tried having the user call it back and resubmit but the hours don't appear to change from ProjectServer_Reporting db.

    Friday, April 6, 2012 4:17 PM

Answers

  • So the team member recalled, entered new info and then submitted, the PM accepted the new updates and published the Project?


    Brian Kennemer - Project MVP
    DeltaBahn Senior Architect
    endlessly obsessing about Project Server…so that you don’t have to.
    Blog | Twitter | LinkedIn

    Friday, April 6, 2012 6:22 PM
    Moderator

All replies

  • So the team member recalled, entered new info and then submitted, the PM accepted the new updates and published the Project?


    Brian Kennemer - Project MVP
    DeltaBahn Senior Architect
    endlessly obsessing about Project Server…so that you don’t have to.
    Blog | Twitter | LinkedIn

    Friday, April 6, 2012 6:22 PM
    Moderator
  • I was wrong... hours do appear changed as expected... after i figured out my odc in excel was hooped...

    :)

    Friday, April 6, 2012 6:43 PM
  • Oh good. That damn refresh will get you every time. ;-)

    Brian Kennemer - Project MVP