  • I am deploying a scheduled task via GPP.  The task deploys fine.

    It is run manually by a support tech to update some files via robocopy.  It is also configured to run with an associated domain account.

    The task starts fine and judging by the logs associated with the robocopy procedure it completes fine.  But the scheduled tasks log shows it started but there is no entry about it finishing.

    Wednesday, April 3, 2013 8:49 PM

Answers

  • Check using ProcessMonitor if the process has actually ended or is still in running state.

    http://live.sysinternals.com/Files/ProcessMonitor.zip

    Also, you can set the option "Stop the task if it runs longer than : XX" Specify a time here and check. 


    Arnav Sharma | Facebook | Twitter Please remember to click “Mark as Answer” on the post that helps you, and to click “Unmark as Answer” if a marked post does not actually answer your question. This can be beneficial to other community members reading the thread.


    Friday, April 5, 2013 9:46 AM