What are the units of numbers displayed in the Requirement Details? (2013) RRS feed

  • Question

  • Hello,

    What are the units of numbers displayed in the Requirement Details of the Resource Analysis page (Portfolio Analysis)

    For a project I entered 10 days for several months in its Resource Plan, while the Requirement Details page displays 0.45; 0.48; 0.43....

    2nd question: If I change the workload in the Resource Plan, save it and publish, how can I refresh the data in  Requirement Details of the Resource Analysis page

    Thanks 

    Sunday, October 11, 2015 2:58 PM

Answers

  • Hi,

    The numbers in the resource requirement details are FTE (full time equivalent). Meaning if you have a workload of 44 days for 1 month for one role, you'll have 2 FTE since a month is more or less 22 days.

    For y our second question, unfortunately, you cannot refresh a portfolio after having updated your project plan. You need to create a new portfolio.


    Hope this helps,