Project 2010 - Scheduling Question RRS feed

  • Question

  • Hi Everyone,

    I am a bit of a noob with the way Project schedules work (more of a back end kind of guy :))

    I picked up a strange issue, and would like to ask the community's advice on this.

    The hours per day for this specific instance must be 7.5 so I have changed the Standard calendar ( I changed the the [Default] week in Work Weeks to be from 8:00AM to 12:45PM, and again from 1:45PM to 4:30PM).

    However, if I go into MSP, connect to the server, create a task for 1d, and assign a resource to it (with the standard calendar applied), it defaults to 8h for Work.

    Is there something that I might be missing here?  Please help :)

    Thanks

    Nico