can % Complete and % work Complete be defferent RRS feed

  • Question

  • Is there a possibility that % Complete and % work Complete for a same task differs? Because I see on one of the tasks there are 2 different values in these fields, please suggest.
    Monday, March 3, 2014 10:12 AM

Answers

  • Yes it is possible that % Complete & % Work Complete for the same task can be different. % Complete uses duration for the calculation purpose and formula goes as Actual Duration/Duration; while % Work Complete uses Work to calculate % - Actual Work/Work. Say if 2 resources are assigned at a task and they update different Actual Work & Remaining Work for a day it would make % complete & % work complete different for same task.


    Sapna Shukla

    Monday, March 3, 2014 10:35 AM