Critical path does not highlight RRS feed

  • Question

  • I am using Microsoft project 2010. I previously highlighted some tasks and then change them back to “no highlight”.

    Now when I use the "highlight critical tasks" tool, those tasks do not change color. How can I fix the problem?

    Thank you

    Thursday, October 15, 2015 8:39 PM

All replies

  • Try selecting the tasks then Task, Clear, Clear Formatting

    If that doesn't work create a new Gantt Chart View.


    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz

    Thursday, October 15, 2015 8:56 PM
    Moderator
  • M-CAN --

    In addition to the excellent answer by my colleague, Rod Gill, you could also reset the Gantt Chart view back to its default settings.  To do this, click the Task tab to display the Task ribbon.  In the View section of the Task ribbon, click the Gantt Chart pick list button and select the Reset to Default item.  In the confirmation dialog, click the Yes button.  Hope this helps.


    Dale A. Howard [MVP]

    Friday, October 16, 2015 12:31 PM