  • Question

  • Can anyone tell me where to find the "Modified by" field for schedule changes in Project Server 2010 ? It is easy to find for lists and libraries but nobody seems to know where it lives for the project schedule. We have multiple Project Managers updating some schedules and would like to be able to tell who made the most recent updates.

    Thanks for any info.

    Jeff

    Friday, March 14, 2014 8:23 PM

All replies

  • Hi Jeff,

    Based on the PS2010 SDK and Reporting DB schemes, the "modified by" information is not available directly in the RDB. What you can easily get will be the project last modified date (ProjectModifiedDate) in the MSP_EpmProject_UserView and find the ProjectModifiedDate. 

    There is another solution "out-of-the-box": retaining the queue logs, navigate to Manage queue settings and change the cleanup age limit, which essentially will retain a level of history who saved / published the plan when.

    Finally as an alternative solution you can have a simple macro in  project professional which can keep logging activities as required in a custom table for auditing purposes.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS