    I created 2 tasks, Duration: 5d on next week (so Near Future)

    I assigned the same resource on the 2 tasks, saved and published the project.

    In her PWA "Assignments" page the resource can see her new assignments. In her Availability page too.

    But in her Tasks view, these assignments never appeared. In fact there is no Near Future Planning Window for this resource.

    What could be the cause of this phenomenon?

    Thanks

    Thursday, February 24, 2011 11:24 AM

Answers

  • Hi,

    two more questions, the second one for me to reproduce:

    1. By any chance, is assgnment owner for these tasks someone else?
    2. What is your value of "Near Future Planning Window"?

    Regards
    Barbara

    • Marked as answer by WLID1966 Thursday, February 24, 2011 12:20 PM
    Thursday, February 24, 2011 11:59 AM
    Moderator

All replies

  • Hi,

    could you please verify that this resource has booking type Committed? If you see it in Assignments, but not in Tasks, this is my first idea.

    Regards
    Barbara

    Thursday, February 24, 2011 11:34 AM
    Moderator
  • Hi Barara,

    Yes,   this resource has booking type Committed.

    Thursday, February 24, 2011 11:48 AM
  • Hi,

    two more questions, the second one for me to reproduce:

    1. By any chance, is assgnment owner for these tasks someone else?
    2. What is your value of "Near Future Planning Window"?

    Regards
    Barbara

    • Marked as answer by WLID1966 Thursday, February 24, 2011 12:20 PM
    Thursday, February 24, 2011 11:59 AM
    Moderator
  •  

    1. By any chance, is assgnment owner for these tasks someone else?  : Yes !
    2. What is your value of "Near Future Planning Window"?  : 2 weeks
    Thursday, February 24, 2011 12:17 PM
  • Barbara,

    Yes, you are right : these tasks are in the Assignment owner "Tasks" page.

    Thursday, February 24, 2011 12:20 PM
  • And this "someone else" can't see these tasks? Tasks are only displayed on Assignment Owner's Task page.

     

    Thursday, February 24, 2011 12:20 PM
    Moderator
  • WLID1966 --

    So, now you know by experience how the Assignment Owner field works!  :) Did you specify the other person as the Assignment Owner intentionally?  If not, then I would suspect your Project Server administrator set that other person as the Default Assignment Owner for the resource in PWA.  The key question now is, "Who is supposed to report progress on this task?"  If it is the person actually assigned to the task, then you need to make him/her the Assignment Owner for the task.  And if this person is supposed to report progress on every task he/she is assigned to in every project, then the Project Server administrator needs to specify him/her as the Default Assignment Owner on his/her user account in PWA.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Friday, February 25, 2011 12:41 AM
    Moderator