Network view in Project Professional is not displaying some task links RRS feed

  • Question

  • I am experiencing a problem with Project Professional in the network view. Certain tasks do not show a dependency link line, even though the task does have actually have predecessors and successors in the task details form, and the dependency IS being honored in the schedule calculations. This is an intermittent problem with different plans I have built. Right now it is happening with just a single task in a plan network of 250 tasks. 
    Tuesday, December 20, 2016 11:15 PM

All replies

  • Mel,

    What version of Project are you using? Is it updated with the latest cumulative update? If not, or you're not sure, run Windows Update.

    Does the link line show up in the Relationship Diagram for that task?

    If you Save As the plan to a new name and then delete all but a few tasks that are linked to the "rogue task", does the link line show up now?

    Could you show us a screen shot showing the Gantt display on top and the Network Diagram on the bottom (split view)?

    John

    Wednesday, December 21, 2016 1:44 AM